Chvaletice Power Plant
Renew of Unit 3 and 4 and SNCR Boiler Unit 2 of the coal fired thermal power plant in the Czech Republic.

Facts:
Client: KRÁLOVOPOLSKÁ RIA, a.s., Czech Republic
Capacity: 4x200 MWe
Project period: 7/2015 - 6/2017
Description of project: Complete renew of 2 units, each 200 MW, pulverized coal fired boilers and Selective non-catalytic reduction in Thermal Power Plant Chvaletice, Czech Republic.
Services by ÅF:
- Participation in the project development phase as technical consultant
- Overall Design coordination, Design review
- Boiler Island Design coordination, Design review
- SNCR Boiler Until 2 Design coordination, Design review
- TG Island Design coordination, Design review
- On-site inspection and supervision