Lunna and Gunillaberg Wind Farms

Construction Monitoring for Lunna and Gunillaberg wind farms in Sweden.

Scope:

  • In two wind farms with in total 7 x Vestas V100-2.2 MW ÅF did the construction monitoring on behalf of the client.
    • Review of documentation provided by the seller.
    • Milestone inspections during construction.
    • Inspections of cable installations
    • Inspections of foundations before, during and after grouting
    • Inspection of turbine parts before erection
    • General inspections during erection, test & completion
    • Monthly reporting – Civil & Electrical works