Brista Waste-to-Energy Plant
Consulting services for a new Waste-to-Energy Plant in Brista, Sweden.
Client: Fortum Värme & Stockholm City, Sweden
Consulting services for a new Waste-to-Energy plant in Brista.
Project main scope:
Consulting services to pre-design a new waste-to-energy plant with a capacity of 280 000 t/year. Grated boiler (80 MWf); Fuel and slag handling; semidry fluegas system + fg condenser; turbine; BOP; civil works; electrification; automation; and DCS system.
Project period: 2009 - 2010
ÅF's services:
- Feasibility study (grate and fluidised bed were evaluated);
- Pre-engineering study;
- Main equipment tendering: Preparing ITT´s for binding tenders; Tender evaluation; and Preparation of contracts for main equipment.