Lot 1 Transmission Line and Substations in Nigeria
Lot 1, 330/132/33 kV Makurdi–Jos transmission line and associated substations Markurdi (New) and Jos (Ext.) in Nigeria

Project description:
- 1 x 330 kV DC transmission line, 286 km
- 1 x 150 MVA, 330/132/33 kV substation, including transformer, bays, shunt reactors for reactive power compensation, etc. equipment
- 1 x 60 MVA, 330/132/33 kV substation, including transformer, bays, shunt reactor, etc. equipment
- 1 x 150 MVA, 330/132 kV substation, including transformer, bays, shunt reactor, etc. equipment
ÅF's services:
- Project Management
- Tenders evaluation and contract negotiations
- Kick-off for contract effectiveness
- Detail design check and approval
- Site Supervision
- Project monitoring
- Coordination and interfacing of all parties involved in the implementation
- Monitoring Schedule of performance, including meeting documentation, bond and guarantees, cost controlling
- Establishment of procedures, rules and structures for quality, quantity, safety, cost and work progress monitoring
- Commissioning
- Training
- Reporting