Modification of 130 t/h PC boiler with back pressure turbine to BFB for biofuels, sludge and RDF in South Korea.
Project description:
Modification of 130 t/h PC boiler with back pressure turbine to BFB for biofuels, sludge and RDF.
Project period: 2007 - 2009
ÅF's services:
- Pre-Engineering for local detailed engineering and purchasing of new fuel handling, new convective boiler
- New Air and FGR system, New Flue Gas Cleaning
- New Ash Handling system, DeNOx by SNCR
- New Combustion Control, Turbine modifications
- Detailed Engineering for the rebuilding of the existing PC boiler to BFB
- Commissioning