Project description: 

  • 1 x 330 kV DC transmission line, 286 km
  • 1 x 150 MVA, 330/132/33 kV substation, including transformer, bays, shunt reactors for reactive power compensation, etc. equipment
  • 1 x 60 MVA, 330/132/33 kV substation, including transformer, bays, shunt reactor, etc. equipment
  • 1 x 150 MVA, 330/132 kV substation, including transformer, bays, shunt reactor, etc. equipment

ÅF's services:

  • Project Management
  • Tenders evaluation and contract negotiations
  • Kick-off for contract effectiveness
  • Detail design check and approval
  • Site Supervision
  • Project monitoring
  • Coordination and interfacing of all parties involved in the implementation
  • Monitoring Schedule of performance, including meeting documentation, bond and guarantees, cost controlling
  • Establishment of procedures, rules and structures for quality, quantity, safety, cost and work progress monitoring
  • Commissioning
  • Training
  • Reporting