Substation Jakobsberg

Rehabilition in Switzerland

Description of project:

150/12 kV Substation Jakobsberg, Replacement of indoor  air-insulated by SF6 gas-insulated switchgear:

  • Underground Substation
  • 8 x 150 kV line bays
  • 150 kV double busbar with by-pass bar
  • 30 x 12 kV switchgear bays
  • 150 & 12 kV cable connections
  • Control, metering, protection,
  • Auxiliary services

ÅF's services:

  • Project Management
  • Tendering, Evaluation, Contracts
  • Detail Design
  • Design Approval
  • Site Supervision
  • Monitoring Schedule of performance
  • Commissioning
  • Project Accounting