ECSEE Serbia project

110/35/10 kV Substations and 110 kV OHTL in Serbia

Project description:

  • Construction of 3 new 110 kV overhead transmission lines of total 32 km
  • Construction of a new 110/35/10 kV substation in Mitrovica, including protection and control
  • Extension of the existing 110/35/10 kV substation in Arilje, incl. extension of protection and control
  • Project financed under a loan from the World Bank (IBRD number 4090-ICB-01)

ÅF's services:

Main Task A: Development of a Master Work Plan for Implemen¬tation of the first phase of the Project

  • Review of engineering design, drawings and technical specifi¬cations of the substations and associated TL
  • Review of the bidding documents and contracts (if already awarded) for the substations and associated transmission lines
  • Review with EPS and EMS of their implementation plans and time schedules for the construction of the substations and trans¬mission lines to ensure well coordinated activities and obtain Permits
  • Development and preparation of a Master Work Plan for complete and successful implementation of the Project

Main Task B: Monitoring and Coordinating the Implementation Activi¬ties of the first Phase of the Project Implementation

  • Review of reports on manufacturing , inspection, factory and site testing and delivery of supplied equipment to ensure compliance with the Master Work Plan
  • Review of factory inspection and test reports for major procured equipment to ensure compliance with the equipment specifications
  • Ensure that all necessary materials and equipment for the overhead transmission lines have been made available by EMS in compliance with the Master Work Plan
  • Review of drawings, specifications and work schedules submitted by the contractors to ensure compliance with the technical specifications and the Master Work Plan
  • Review of progress reports prepared by EPS, EMS and the contractors and inspection of the construction sites to monitor and determine the actual progress
  • Ensure that the work activities are well coordinated between the substation and transmission line parts and that the systems will be completed in accordance with the Master Work Plan
  • Preparation of monthly reports reflecting the progress during each month of the construction and proposal of mitigation measures in case of deviations
  • Immediately report to EPS in case of any major obstacles or deviations in the Master Work Plan delaying the project implementation
  • Verification of full completion of all work, successful testing and commissioning of the facilities at project end.