Description of Project
ÅF was awarded contracts for Owner’s Engineering Services for construction of a lignite-fired power plant in Stanari, Bosnia & Herzegovina. The plant is scheduled for commercial operation in 2014.

Our services
We prepared the feasibility studys, conceptual design, RFT documents and conducted bid valuation for two different plant alternatives: 420 MW with a supercritical PC boiler and 350 MW with a subcritical CFB boiler.