Wind Farm Vänern
Main responsibility for the planning of the wind farm Vänern, an offshore wind farm consisting of 10 turbines in the lake of Vänern in Sweden.

Description of project:
Project period 2005 - 2009.
The project comprised having the main responsibility for the planning of the wind farm Vänern, an offshore wind farm consisting of 10 turbines in the lake of Vänern. The nominal power output of the wind farm is 30-40 MW.
ÅF's services:
Coordination of Environmental Impact Assessment (EIA); environmental permitting; building permit and concession for power line; preparation of procurement documentation; acting as environmental coordinator and supervisor during construction works as well as support in the process of defining environmental responsibilities and other legal requirements between the parties involved.