Project included:
Modernization and safety projects. Change of switchgear for galvanization- and coating line.

  • Preliminary project and budget for the project
  • Stage1, move relay based equipment to PLC in the coating line. Commissioned in fall 2010
  • Stage2, exchange of main switchgear. Commissioned in summer 2011
  • Stage3, exchange of oven switchgear for galvanization line. Commissioned in summer 2010
  • Stage4, exchange of control system for galvanization line. Commissioned in summer 2012

ÅF:s deliverance in the assignment:

  • Pre study
  • Budget
  • Project management
  • Purchase inquiry documents for switchgear and switchgear assembly
  • Electrical design
  • Commissioning
  • Documentation

ÅF:s Technical disciplines in the assignment:
Electrical, automation and project management